Luas Capacity Enhancement

Project Title Luas Capacity Enhancement
   Interior luas
Project Description
Capacity Enhancement is divided into 3 phases:
 
Phase 1 - 10 metre extensions of the original 26 Red Line trams
Phase 2 - 8 additional trams for Red and Green lines
Phase 3 - Review of future capacity requirements on Green Line
 

Projected Completion Date
Phase 1 - 2008 - Completed
Phase 2 - 2009 - Completed
Phase 3 - Under Review
Current Status of Project
Phase 1
The objective of Phase 1 of this project was to deliver an additional 40% capacity on the Luas Red Line (to Tallaght) through the extension of all 26 trams on that line from 30 to 40 metres, similar to those used on the Green Line. This project was completed in May 2008.
 
Phase 2
Phase 2 of this project was the provision of eight new trams for the Red/Green Luas lines. The new trams became fully operational and available for passenger service at end September 2009 marking the completion of this project.
 
Phase 3
The RPA is also keeping under review the options and timescale for providing further capacity on the Green Line (to Sandyford), such as increasing the frequency of services and increasing the length of trams.
 