Status and revised target date for each project and those that have missed original target

Date: 17 June 2008

 Dáil Question
No: 147


*To ask the Minister for Transport the status and revised target completion dates for each project under Transport 21; the number of projects that have missed their original target deadline; and if he will make a statement on the matter.
- Pat Rabbitte. (Nominated by: Thomas P. Broughan).

 
Answered by the Minister for Transport
(Noel Dempsey T.D.)

REPLY

Transport 21 represents the largest capital investment commitment ever made by Government to the development of transport infrastructure in this country.

At the launch of Transport 21, the Government identified the projects in the national roads, public transport and regional airports sectors that it wishes to see prioritised for development in the ten-year period from 2006 to 2015.

The completion dates given for Transport 21 projects at the launch of the investment programme were indicative only and subject to the requirements of (i) public consultation, (ii) relevant statutory processes and (iii) the procurement and contract award process. The current status and indicative completion dates for major projects can be found on the Transport 21 website (www.transport21.ie).